HighlightsGravity plant and 650kVA generator have been delivered to the Barani SiteSite preparation and civil construction activities are advancing with equipment, construction materials and supporting resources being mobilized to the active work areasPlant erection and commissioning activities are planned through October, followed by ramp-up and initial processing during November 2026Water on site confirmed by borehole drilling with final hydrogeological report pendingInitial gold recovery is…